Faq

How to fix Onduline Verges and Edges

COVERING WITH AN ONDULINE SHEET CORRUGATION

1 - Fasten bargeboard level with the underside of ONDULINE corrugation and overhang corrugation.
2 - Fold down and nail into position.

COVERING WITH AN ONDULINE SHEET CORRUGATION

 

COVERING WITH AN ONDULINE RIDGE UNIT

1 - Fasten bargeboard level with top of ONDULINE sheet.
2 - The ONDULINE ridge is then overlaid and nailed into position.

COVERING WITH AN ONDULINE RIDGE UNIT

COVERING WITH AN ONDULINE VERGE UNIT

1 - Fasten bargeboard level with top of ONDULINE sheet.
2 - The ONDULINE verge is then overlaid and nailed into position.
3 - Overlaps for verges should be a minimum of 20 cm.

COVERING WITH AN ONDULINE VERGE UNIT

COVERING WITH THE UNIVERSAL MULTIPURPOSE EAVES TRAY

1 - Fasten bargeboard level with top of finished ONDULINE roof.
2 - Covering with the universal multipurpose eaves tray is then overlaid and nailed into position.

COVERING WITH AN ONDULINE MULTIPURPOSE EAVES TRAY

See full technical installation guide.